Ave. Eth. Antistatis 34, Basilies 715 00
LOCATION

Maryborough, Queensland, Australia

POWER

98 MW

PANELS

286.500

PILES

41.446

PROJECT DETAILS

Start date:

Finish date:

EPC Contractor:

 

 May 2018

 Sep 2018

Biosar Australia

 

SUSAN RIVER SOLAR PARK, QUEENSLAND

This project was done in Australia in Maryborough Queensland. It had a power of 98 MW, 286,500 panels and was implemented in 2018. The General Contractor was BIOSAR AUSTRALIA of the ELLAKTOR group.
We did the piling work,  & the installation of the Panels for 50% of the project.